Deconstructing Subsea Cable Installation: LIVINGSTONE at South Fork Wind
- Jan 24
- 3 min read

We tracked DEME’s cable lay vessel LIVINGSTONE to break down the installation campaign of both export cable (EC) and inter-array cable (IAC) scopes for Ørsted’s South Fork Wind project. Our study reveals the major cost drivers of subsea cable installation for an early U.S. Offshore Wind project.
Project Overview
Project: South Fork Wind (Ørsted)Cable Installation Vessel: LIVINGSTONE (DEME)Shore Landing: Wainscott Beach, Long Island
No. of Export Cables: 1
No. of Offshore Sub-Stations (OSS): 1Export Cable Distance: 66 milesInter-Array Cable Distance: 21 miles
Export Cable Characteristics
Single export cable
Installed in two segments
One mid-corridor jointing operation
Logistics Profile
5x port calls to Providence, RI (Prov Port), totaling 16 days
2x load-out calls to Nexans Goose Creek, SC:
First visit: initial export cable segment, 14 days
Second visit: second export cable segment, 13 days
Cable lay and post-lay trench & burial scopes were both performed by LIVINGSTONE
The inter-array cable was delivered to Prov Port via transatlantic heavy lift vessel and was subsequently loaded onto LIVINGSTONE
Campaign Duration Breakdown
Total tracked campaign time: 3,532 hours (147.2 days)
Time Allocation by Scope
Scope | Days | % of Total |
Transit | 8.5 | 6% |
Idle | 31.4 | 21% |
Pre-Lay Survey | 2.6 | 2% |
EC Lay 1 | 4.7 | 3% |
EC Shore Pull-In | 1.5 | 1% |
EC Burial 1 | 11.9 | 8% |
Jointing | 9.0 | 6% |
EC Lay 2 | 4.9 | 3% |
EC Burial 2 | 16.4 | 11% |
Mattress Install | 3.5 | 2% |
EC Post-Lay Survey | 3.5 | 2% |
IAC 1 | 4.4 | 3% |
IAC 2 | 1.0 | 1% |
IAC 3 | 35.5 | 24% |
Key Observations
1. Idle Time Was Material
Idle time accounted for 31.4 days (21%) of total campaign duration.
For capital-intensive assets such as DP cable lay vessels, this represents meaningful cost exposure. Idle time may reflect:
Weather constraints
Port scheduling
Equipment readiness
Regulatory or inspection delays
Sequencing between export and array scopes
Understanding the drivers behind idle time is essential for future cost optimization.
2. Burial Was the Dominant Export Cable Activity
Export cable burial alone consumed:
Burial 1: 11.9 days
Burial 2: 16.4 days
Total burial: 28.3 days
That exceeds total export lay time (9.6 days combined for Lay 1 and Lay 2).
This reinforces that burial — not lay — is typically the rate-determining step in export cable installation.
3. Jointing Was Non-Trivial
The single mid-corridor jointing operation required 9 days, representing 6% of total campaign duration.
Even a single joint introduces material schedule exposure.
4. Inter-Array Scope Was Concentrated in One Extended Campaign
The third IAC campaign (IAC 3) alone consumed 35.5 days (24% of total campaign time).
The distribution suggests:
A prolonged final array push
Possible weather sensitivity
Or concentration of remaining strings
Productivity
Export Cable Work (Excluding Survey)
48.4 days total
0.73 days per mile
Inter-Array Cable Work (Excluding Survey)
40.8 days total
1.94 days per mile
Inter-array installation required nearly 3x more time per mile than export cable installation.
This differential likely reflects:
Increased complexity of multiple short strings
Repeated touchdown and positioning
Array routing geometry
Smaller campaign batches
Export cable installation benefits from longer continuous lay runs, while inter-array work introduces higher operational friction per mile.
Our Takeaways
Several themes emerge from this vessel-level analysis:
Idle and non-lay activities consume a significant share of campaign duration.
Burial — not lay speed — governs export cable schedule risk.
Jointing events introduce discrete schedule blocks that must be modeled explicitly.
Inter-array installation is structurally less efficient per mile than export cable installation.
For developers and financiers, this has implications for:
Contingency modeling
Vessel day rate exposure
Weather window risk
Supply chain synchronization
Port logistics planning
Breaking down vessel behavior at the activity level reveals what actually governs schedule and cost performance. For developers and EPC contractors, this visibility enables more deliberate allocation of installation scopes, improved utilization of high-value assets, and better management of execution and risk factors in U.S. Offshore Wind campaigns.



Comments