top of page
Search

What Early U.S. Offshore Wind Projects Reveal About WTIV–Feeder Productivity

  • Jan 24
  • 3 min read
AEOLUS (Jan De Nul)
AEOLUS (Jan De Nul)

Early U.S. Offshore Wind projects relied on European wind turbine installation vessels (WTIVs) operating in coordination with U.S.-flagged feeder barges to comply with the Jones Act. We looked at the compared installation performance between the first to commercial scale U.S. Offshore Wind projects to better understand productivity and workability of the feeder barge solution.


Our study evaluated installation cycle performance from two early U.S. offshore wind projects:


South Fork Wind (Ørsted)

WTIV: AEOLUS (Jan De Nul)

Feeder Configuration: One feeder barge with ocean tugs (Crowley)


Vineyard Wind (CIP / Avangrid)

WTIV: SEA INSTALLER (DEME)

Feeder Configuration: Two feeder barges with ocean tugs (Foss)

 

We evaluated installation cycle characteristics, feeder interaction efficiency, weather exposure, and overall time-in-position for wind turbine generator (WTG) installations.

 

Methodology


South Fork Wind – AEOLUS

  • 11 WTG installations reviewed

  • Installations 4, 6, and 7 excluded due to AIS coverage gaps

  • Analysis reflects early-project performance


Vineyard Wind – Sea Installer

  • First 11 WTG installations reviewed to align learning curve stage with South Fork

  • First installation excluded from summary due to extended initial waiting-in-position time

 

Each installation cycle was segmented into:

  • WTIV Time in Position

  • Pre-Feeder Barge Time

  • Feeder Barge Alongside Time

  • Post-Barge Time

  • Waiting-on-Weather

  • Total Cycle Time per WTG

  • Barge Workability (Barge Alongside Time / Barge On-Scene Time)

 

Project 1: AEOLUS – South Fork Wind

Metric

Average

Min

Max

Total

WTIV in Position (hr)

149

16

409

1,342

Pre-Barge (hr)

67

0

299

606

Barge Alongside (hr)

42

18

119

374

Post-Barge (hr)

118

19

328

1,058

Waiting-on-Weather (hr)

39

0

218

355

Total Cycle Time (days)

11

5

25

99

Barge Workability

39%

7%

90%

 Observations

  • Average total installation cycle: 11 days per WTG

  • Feeder barge was alongside only 39% of the time the barge was available in the field

  • Weather impact present but not dominant relative to total cycle time

  • Installation productivity appears strongly influenced by feeder synchronization

 

Project 2: Sea Installer – Vineyard Wind

Metric

Average

Min

Max

Total

WTIV in Position (hr)

393

144

819

3,929

Pre-Barge (hr)

46

0

224

456

Barge Alongside (hr)

393

144

819

3,929

Post-Barge (hr)

141

10

259

1,409

Waiting-on-Weather (hr)

160

0

769

1,599

Total Cycle Time (days)

18

7

38

178

Barge Workability

37%

40%

37%

Observations

  • Average total installation cycle: 18 days per WTG

  • Feeder barge was alongside only 37% of the time the barge was available in the field

  • Significantly longer WTIV time in position relative to South Fork

  • Higher waiting-on-weather exposure

  • Greater variability and weather sensitivity observed in early campaign phase

 

Comparative Insights


1. Total Cycle Time

  • AEOLUS: 11 days per WTG

  • SEA INSTALLER: 18 days per WTG, 60% greater than AEOLUS


2. WTIV Time in Position

SEA INSTALLER averaged more than 2.5x the time in position per turbine compared to AEOLUS.

This may reflect:

  • Different site conditions

  • Weather exposure

  • Project execution strategy

  • Vessel operating profile

  • Early campaign inefficiencies


3. Feeder Barge Performance

Barge workability was similar across projects (~37–39%).

This suggests that:

  • Adding a second feeder barge does not necessarily translate into materially higher alongside utilization

  • WTIV productivity is not purely a function of feeder count

  • Synchronization and sequencing may matter more than asset quantity

  • Motion compensation technologies may not have been as effective as expected


4. Weather Sensitivity

Sea Installer experienced materially higher average waiting-on-weather time.

Weather exposure appears to amplify total cycle variability, particularly when installation campaigns extend over longer durations per turbine.

 

Strategic Implications

These early U.S. offshore wind campaigns suggest several structural observations:

  • WTIV idle time is substantial relative to productive barge interaction time

  • Feeder synchronization appears to be a primary driver of cycle efficiency

  • Weather exposure compounds inefficiencies when cycle duration extends

  • Simply increasing feeder count does not guarantee higher productivity


For developers, EPC contractors, and lenders, installation cycle duration directly impacts:

  • Project schedule risk

  • Contingency requirements

  • Vessel day rate exposure

  • Insurance and financing cost

  • Weather window strategy


As the U.S. market wrestles with the Jones Act feeder model, understanding the real-world performance of feeder models is critical in evaluating future capital allocation and risk models. Early projects offer valuable empirical data on installation cycle mechanics under feeder-based logistics structures. Future analysis will reveal learning curve effects and mid-campaign performance improvements as more installation data becomes available.

 


 
 
 

Comments


bottom of page